CONSTRUCTION WORK UPDATE   2021 Annual Road Resurfacing Program

Old Bridge Township contractor, Meco Inc., will beginning milling and resurfacing various streets within the town. The following work is anticipated, weather permitting, from Friday 9/10/2021 to Friday 9/17/2021:

  • Raritan Boulevard - (Ocean Ave to Central Ave – Half Width) & (Lake Ave to Ocean Ave – Half Width)
    • Paving on (9/10)
  • Sunset Avenue - (Whole Street – Half Width)
    • Paving on (9/10)
  • Washington Avenue - (Mercury Circle to Iliad Road)
    • Paving on (9/10)
  • Homer Road - (Whole Street)
    • Paving on (9/10)
  • Brown Court - (Whole Street – Half Width)
    • Milling on (9/10) and Paving on (9/14)
  • Cornell Road - (Whole Street – Half Width)
    • Milling on (9/10) and Paving on (9/14)
  • Colby Court - (Whole Street – Half Width)
    • Milling on (9/10) and Paving on (9/14)
  • Hamilton Court - (Whole Street)
    • Milling on (9/14) and Paving on (9/14)
  • Partridge Road – (Part – Warne Road to Lambertson Road)
    • Milling on (9/14) and Paving on (9/15)
  • Maiden Lane – (Part – Archery Court to Rose Lane)
    • Milling on (9/15) and Paving on (9/15)
  • Midsummer Drive – (Whole Street)
    • Milling on (9/15) and Paving on (9/16)
  • Troilus Drive – (Whole Street)
    • Milling on (9/16) and Paving on (9/16)
  • Ellen Circle – (Part – Norman Lane to Dwelling #23)
    • Milling on (9/16) and Paving on (9/17)
  • Nathan Drive – (Part – Fela Drive to Amy Court)
    • Milling on (9/16) and Paving on (9/17)
  • Glen Avenue – (Whole Street)
    • Milling on (9/17)
  • Green Street – (Part – Dwelling #197 to Dwelling #287)
    • Milling on (9/17)
  • Tunica Court – (Whole Street)
    • Milling on (9/17)

Should you have any questions please contact the Old Bridge Township Engineering Department at 732.721.5600 x2302.